International Journal of Scientific & Engineering Research, Volume 3, Issue 10, October-2012 1
ISSN 2229-5518
Irfan Ali* and S. Suhaib Hasan
The present paper, considered the allocation problem of repairable components for a parallel-series system as a multi-objective optimization problem for two different models. In the first model, the reliability of subsystems are considered as different objectives. While in the second model, the cost and time spent on repairing the components are considered as two different objectives. Selective maintenance operation is used to select the repairable components and a fuzzy programming algorithm is used to obtain compromise allocation of repairable components for the two models under some given constraints. A numerical example is also given to illustrate the procedure.
.
-----------------------*---------------------
m
1 (1 r ) ni ai di
(2)
In every industry, systems are used in the production of
goods. If such systems deteriorate or fail, then effect can
R = i
i 1
be wide spread. System deterioration is often reflected in higher production cost, time lower product quality and quantity. The system maintenance decision is taken on
The repair time constraint for the system is given as
m
ti d i exp ( i d i ) T0
i 1
(3)
the basis of the state condition of the system (i.e. whether
where ti
is the time required to repair a component in
the system is good or bad). The aim is to present a model
of reliability improvement maintenance policies that
i th subsystem and
exp (i
ai ) is the additional time
minimizes the total cost and time spent on maintaining a system. For this purpose, we consider a system which is a series arrangement of m subsystems and performing a
spent due to the interconnection between parallel
components (Wang et al. (2009)).
The repair cost constraint for the system is defined as
m
sequence of identical production runs.
c d
exp ( d ) C
(4)
Suppose that after completion of a particular production
i i
i1
i i 0
run, each component in the system is either functioning or failed. Ideally all the failed components in the subsystems are repaired and then replaced back prior to the beginning of the next production run. However, due to constraints on time and cost, it may not be possible to repair all the failed components in the system. In such
situation, a method is needed to decide which failed
where exp (i ai ) is the additional cost spent due to the interconnection between parallel components (Wang et al. (2009)).
However, in the event when the reliability of each
subsystems are of equally serious concern. Let us consider, for instance, the following multi-objective problem (see Ali et al. (2011c)):
components should be repaired and replaced back prior to the next production run and the rest be left in a failed
Maximize R1 , R2 , , Rm
(i)
condition. This process is referred to as selective maintenance (See Rice et al. 1998). In the selective maintenance the number of components available for
the next production run in the i th subsystem will be
subject
m
ti d i
i1
m
to
exp ( i d i ) T0
(ii ) (5)
(ni
ai ) d i , i 1, 2, ..., m
(1)
ci d i exp ( i d i ) C0
i1
(iii )
The reliability of the given system is defined as
0 d i ai , i 1,2,..., m and integers (iv)
IJSER © 2012 http://www.ijser.org
International Journal of Scientific & Engineering Research, Volume 3, Issue 10, October-2012 2
ISSN 2229-5518
where
R = 1 (1 r )
ni ai di ,
i 1, 2, ..., m.
constrained optimization developed by LINDO Systems
Ali et al. (2011c) also discussed the situation in which time taken and the cost spent on system maintenance are minimized simultaneously for the required reliability R * (say). The mathematical model of the problem is defined as:
m
Min C ci d i exp i d i
i1
Inc. A user’s guide- LINGO User’s Guide (2001) is also
available. For more information one can visit the site http://www.lindo.com.
To solve multi-objective allocation problem of repairable components defined in equation (5), we apply the fuzzy programming approach (see Mahapatra et al. (2010)). At
and
first, we find the upper bound
U r (best) and lower
m bound
Lr (worst) for corresponding objective
Min T
subject to
m
ti d i exp i d i
i1
(6)
function Z r , r 1, 2,, m .
Let U r = aspiration level of achievement for objective r ,
Lr = lowest acceptable level of achievement for
1 1 r ni ai di
i1
R*
objective r ,
r = U r Lr = the degradation allowance for
0 d i
ai
, i 1,2,..., m and integers
objective r ,
The selective maintenance operation is an optimal decision-making activity for systems consisting of several components under limited maintenance duration. The main objective of the selective maintenance operation is to select the most important component in subsystem. Rice et al. (1998) were the first to deal with the selective maintenance problem. Ali et al. (2011a, 2011b, 2011c) and Faisal and Ali (2012) considered the problem of optimum allocation of repairable and replaceable components for series- parallel system by using selective maintenance.
Fuzzy programming offers a powerful means of
handling optimization problems with fuzzy parameters.
when the aspiration level and degradation allowance for
each objective are specified.
repairable components as a single objective used each time and all other ignored.
objective at each solution derived.
objective w. r. to each solution the pay-off matrix in the main program gives the set of non dominated solution which shown in the following table.
Fuzzy programming has been used in different ways in the past. In (2010), Mahapatra et al. studied the fuzzy programming approach to stochastic transportation problem and many others. In reliability Park (1987),
d (1)
( 2)
Z1
Z11
Z 2
Z12
Z m
Z1m
Mahapatra and Roy (2006), Huang (1997), Dhingra
(1992), Rao and Dhingra (1992) and Ravi et al. (2000)
d Z 21
Z 22
Z 2m
have used fuzzy multi-objective optimization method to
solve reliability optimization problem having several conflicting objectives.
( m)
(1)
Z m1
( 2)
Z m2
( m)
Z mm
This paper presents a new contribution in the field of
where d
, d ,, d
is the ideal solution for the
system reliability optimization for compromise
objective Z1 , Z 2 Z m respectively.
allocation problem of repairable components. A Fuzzy
Let
Zij
Zi (d
), i
1, 2,,
m and
j 1, 2,, m
are
programming algorithm is used to obtain compromise
allocation of repairable components.
the maximum value (best) for each
The multi-objective NLPPS are solved by “Fuzzy programming algorithm” using software package LINGO. LINGO is a user’s friendly package for
objective Zi ,
i 1, 2,, m .
IJSER © 2012 http://www.ijser.org
International Journal of Scientific & Engineering Research, Volume 3, Issue 10, October-2012 3
ISSN 2229-5518
(U r ) and worst (Lr ) for each
In a similar way, we solve multi-objective allocation
objectives corresponding to the set of solution i.e.
U r Z rr and Li MinZ1r , Z 2r ,, Z mr . To satisfy,
problem of repairable components defined in equation
(6); we apply the fuzzy programming approach. At first,
r 1
Z r U r , r 1, 2,, m and constraints (ii), (iii) and (iv)
we find the upper bound
Lr (best) and lower bound
of NLPP (5).
U r (worst) for corresponding objective function
Z r where r 1, 2,, k .
Let Lr = aspiration level of achievement for objective r ,
0
(d ) Z r Lr
Zr ij L
Z r Lr
Lr Z r U r
U r = highest acceptable level of achievement for objective r ,
U r r
r =
U r Lr = the degradation allowance for
1
Z r U r
objective r ,
when the aspiration level and degradation allowance for
If Zr (dij ) 1; then Z r is perfectly achieved,
each objective are specified.
0; Z r
is nothing achieved,
Now construct membership function for model (2)
0 Zr (dij ) 1; then Z r is partially achieved.
defined in equation (6) as,
Z L
1 Z r Lr
r r , r 1, 2,, m
U r Lr
(d ) U r Z r
r
Lr Z r U r
Using max-min/min-max operator, we have
maxmin(1 , 2 ,, m ),
U r Lr
0
Z r U r
then
we have; Max
If Zr
(dij ) 1; then Z r is perfectly achieved,
1
0; Z r is nothing achieved,
2
0 Zr
(dij
) 1; then Z r is partially achieved.
U r Z r
m
Let us define r
U r Lr
, r 1, 2,, k
Z
(d ij );
Next using max-min/min-max operator, we have
where Max r
r i j 1, 2,, m & r 1, 2,, m
max min( 1 ,
2 ,,
k ) ,
Finally we obtained the mathematical programming
then
we have; Max
formulation for equation (5) through fuzzy programming , as follows:
1
Maximize
2
subject to
k
where
1 (1 r ) ni ai di (U
L ) L
m
t d
i i i i
exp ( d ) T
(7)
Max
r
Z r
(d ij
); i j 1, 2,, m & r 1, 2,, k
i i
i 1
m
i i 0
Finally we obtained the mathematical programming formulation for equation (6) through fuzzy
ci d i exp ( i d i ) C0
i1
0
0 d i ai , i 1,2,..., m and integers
programming as follows:
IJSER © 2012 http://www.ijser.org
International Journal of Scientific & Engineering Research, Volume 3, Issue 10, October-2012 4
ISSN 2229-5518
Maximize
Maximize Ri
1 (1 r ) ni ai di
subject to
m
subject to
i 1, 2, m
ti d i exp (i d i ) (U1 L1 ) U1
i 1
m
5
ti d i exp ( i d i ) 60
(9)
i 1
ci d i
exp ( i
d i ) (U 2
L2
) U 2
(8)
i 1
5
c d
exp (
d ) 90
m
1 1 r ni ai di
R*
i i i i i 1
i 1
0
1 d i ai , i 1,2,..., 5 and integers
0 d i ai , i 1,2,..., m and integers
Consider a system consisting of 3 subsystems. The
Using the equation (9) construct a pay-off matrix,
according to every objective with respect to each solution the pay-off matrix in the main program gives the set of non dominated solution which shown in the following table
available time between two production runs for Z Z
repairing and replacing back the components is 60 time 1 2
units. Let the given maintenance cost of the system be 90
Z 3
units. The other parameters for the various subsystems
are given in table 1.
d (1)
d ( 2)
0.9992433
0.9589938
0.9084938
0.9916266
0.9687500
0.9687500
d (3)
0.9589938
0.9084938
0.9990234
The upper bounds for the given model 1 are
U1 0.9992433,U 2
0.9916266,U 3
0.9990234 a
nd lower bound
L1 0.9589938, L2 9084938, L3 0.9687500 .
Using the equation (7), we can formulated the model 1as
Maximize
Subject to
and their optimal solutions
d (i ) ; i 1, 2 and 3
with
(3d )
1 (1 0.55)
1 0.0402495 0.95899
the corresponding values of
are listed below. These
(3d2 )
values are obtained by software LINGO.
1 (1 0.45)
0.0831328 0.90849
1 (1 0.55) (3di ) 0.0302734 0.96875
(10)
m
ti d i exp ( i d i ) 60
i 1
m
ci d i exp ( i d i ) 130
i 1
0
1 d i ai , i 1,2,..., m and int egers
IJSER © 2012 http://www.ijser.org
International Journal of Scientific & Engineering Research, Volume 3, Issue 10, October-2012 5
ISSN 2229-5518
The above problem (10) is solved by the LINGO
Software for obtaining the optimal solution of the
practical utility of the fuzzy programming approach in
system reliability.
problem. We get
0.7741945
and the compromise
solution as d1
3, d 2 4, d 3 3 . The optimal
reliabilities of each subsystem are
R 0.9916962, R 0.9847756, R 0.9921875 .
1 2 3
Repairable and Replaceable Components for a System availability using Selective Maintenance: An Integer Solution; Safety and Reliability society, 31(2), 9-18.
for the desired reliability requirement
R* 0.97
has
been solved and construct a pay-off matrix, according to
every objective with respect to each solution the pay-off
matrix in the main program gives the set of non dominated solution which shown in the following table for
Allocating Repairable and Replaceable Components for a System Availability using Selective Maintenance with probabilistic constraints; American Journal of Operations Research, 1(3):147-154.
d (1)
d (2)
Z1
62.38
64.66
Z 2
141.72
141.30
goal programming approach for finding a compromise allocation of repairable components, International Journal of Engineering Science and Technology, 3(6): 184-195.
The upper bound and lower bond for the model 2 are
U1 64.66, U 2 141.72
and L1 62.38, L2 141.30 .
[5]. Huang, H.Z. (1997); Fuzzy multi-objective optimization decision-making of reliability of series system, Microelectronics Reliability, 37 (3), 447–449.
Maximize
subject to
m
Repairable and Replaceable Components for a System
Reliability using Selective Maintenance: An Integer
Solution, International Journal of Scientific and Engineering
ti d i exp (i d i ) 2.38 64.66
i1
m
Research, 3(5), 1-4.
Systems Inc., 1415 North Dayton Street, Chicago,
c d
exp (
d ) 0.42 141.30
(11)
Illinois-60622 (USA).
i i i i
i1
m
[8]. Mahapatra, D. R., Roy, S. K. and Biswal, M. P. (2010);
Stochastic Based on Multi-Objective Transportation
1 1 r ni ai di
i 1
0.97
Problems Involving Normal Randomness, Advance
0
1 d i ai , i 1,2,..., m and integers
The above problem (11) is solved by the LINGO Software for obtaining the optimal solution of the
Modeling and Optimization, 12 (2), 205-223.
Objective Mathematical Programming on Reliability Optimization Model, Applied Mathematics and Computation, 174 (1), 643-659.
problem. We get
0.0233
and the compromise
reliability, IEEE Transactions on Reliability, R-36, 129-132.
solution as d1
3, d 2 4, d 3 4 .
Optimal Maintenance Plans under Limited Maintenance
This paper is an attempt to utilize Fuzzy programming approach to the solution of optimum compromise allocation of repairable components in a system. Further, a numerical example is presented to demonstrate the
Time, Industrial Engineering Research 98 Conference proceedings.
redundancy apportionment using crisp and fuzzy multi- objective Optimization approaches, Reliability Eng. Syst. Safety, 37, 253-261.
IJSER © 2012 http://www.ijser.org
International Journal of Scientific & Engineering Research, Volume 3, Issue 10, October-2012 6
ISSN 2229-5518
Zimmermann (2000); Fuzzy global optimization of complex system reliability, IEEE Trans. Rel., 8, 241-248.
Multi-objective Approach to Redundancy Allocation Problem in Parallel- series System, IEEE Congress Evolutionary Computation, 582-589.
BIOGRAPHICAL NOTES
Irfan Ali received M.Sc. and M. Phil. in Statistics from Aligarh Muslim University, Aligarh, India. Presently he is pursuing Ph.D. from department of Statistics and Operations research Aligarh Muslim University, Al igarh, India. He has published 16 research papers in national and international journals of reputes. He has also presented 4 research articles in national conferences.
Suhaib Hasan received M.Sc. and M. Phil. in Statistics from Aligarh Muslim University, Aligarh, India. He is a
Associate Professor in the Department of Statistics and Operations research Aligarh Muslim University, Aligarh, India. Mr. Hasan has more than 25 years of experience in teaching and research. His area of interest also includes linear models and econometrics.
IJSER © 2012 http://www.ijser.org